Shahganj to Badi 4-Lane Road Upgrade

The Construction work of 4-laning of Shahganj bypass end to Badi (Package-IV) of NH-146B from design km 102.000 to design km 142.357 covers upgrading a ~40.357 km stretch from Shahganj bypass end to Badi into a 4-lane divided carriageway, incorporating major and minor bridges, VUPs, LVUPs, culverts, service roads, grade-separated junctions, and modern safety provisions, executed under NHAI to strengthen corridor connectivity, reduce travel time, improve traffic safety, and boost socio-economic growth across Sehore and Raisen districts in Madhya Pradesh.

Project At Glance

ParticularsDetails/Status PKG – 4
 Length40.357 Km
 NH No.146 – B
 Project CostRs. 519 Crores
 ConcessionaireM/s Shahganj Badi Highways Pvt. Ltd.
 Independent EngineerM/s Saptagon Asia Pvt. Ltd.
 Date of LOA15.03.2024
 Date of Agreement29.08.2024
 Appointed Date25.03.2025
 Completion Date24.03.2027
 Construction Period730 Days
 Lane Configuration4 Lane
 Bypasses4.807 Km (Baktra 2.500 Km + Badi 2.307 Km)
 Service Road/Slip Road35.830 Km (17.915 km LHS + 17.915 km RHS)
 R.C.C. Side Drain35.830 Km (17.915 km LHS + 17.915 km RHS)
 Junctions46 nos. (Major – 0, Minor – 25, Grade Separated – 21)
 HPCTotal – 27 no. (New – 15 nos., Reconstruction 12 nos.)
 Box CulvertTotal – 17 no. (New – 07 nos., Reconstruction 8 nos., Widening – 2 nos.)
 Culverts on Cross RoadTotal – 46 no. (Box – 32 no., HPC – 14 no.)
 VUP15 nos. (Single Span – 9 & Multi Span – 6)
 LVUP6 nos.
 Minor Bridge12 nos. (Additional 2 no. of bridges are to be retained on LHS)
 Major Bridge01 nos.
 Toll plaza01 nos. (Chainage 114+515)
 Bus SheltersTotal – 21 no.  (11 nos.(LHS) + 10 nos. (RHS))
 RE Wall35.080 Km (17.54 km LHS + 17.54 km RHS)
 Toe Wall740 Mtr. (370 m LHS + 370 m RHS)
 Retaining Wall1.188 Km (594 mtr LHS + 594 mtr RHS)
 Boundary WallEntire Length of Project at BHS
No.MonthRemarks
1.March & April 2025Preview PDF
2.May 2025Preview PDF
3.June 2025Preview PDF
4.July 2025Preview PDF
5.Aug 2025Preview PDF
6.Sep 2025Preview PDF
7.Oct 2025Preview PDF
8.Nov 2025Preview PDF
9.Dec 2025Preview PDF
10.Jan 2026Preview PDF
11.Feb 2026Preview PDF